|
Rulemaking Update:
Environmental Resource Permit (ERP) Streamlining
The SJRWMD began formal rulemaking in April 2004 to
amend its ERP rules to reduce ERP application processing times. Four
of the main parts of this rulemaking are:
1. Revise individual permit thresholds, so that more
permits are staff-issued (increased delegation);
2. Increase permit modifications allowed by letter (expanded letter
modifications);
3. Charge a fee for letter modifications; and
4. Charge a fee for missing copies of permit application in initial
application submittals (5 copies are required by rule)
Among other things, the rule amendments would delegate
to staff the authority to make decisions on the following two
categories of ERP applications that are currently approved by the
Governing Board as individual permits: (1) modifications to individual
ERPs where the work proposed in the modification phase does not exceed
the individual ERP permitting thresholds by itself; and (2) ERP
stormwater applications that propose wetland stormwater management
systems, or alternative treatment or design systems.
Litigation Update:
St. Johns River Water Management District v. Koontz, 861 So.2d
1267 (Fla. 5th DCA 2003)
Koontz applied to SJRWMD for an environmental resource
permit (“ERP”) to fill 3.4 acres of wetlands for a 3.7-acre commercial
development. His proposed mitigation constituted preservation of
on-site wetlands at a 3 to 1 ratio. SJRWMD denied the application due
to insufficient mitigation and advised Koontz that additional
mitigation would allow issuance of a permit. Koontz did not challenge
the permit denial through Chapter 120, Florida Statutes. Instead, he
sued SJRWMD in Circuit Court, claiming that the requirement for
additional mitigation constituted a taking of his property.
Significantly, Koontz stipulated before trial that additional
mitigation would not deny him all or substantially all economic or
beneficial use of the property.
In October 2002, the Ninth Circuit Court, in and for
Orange County, ruled that SJRWMD’s denial of the ERP permit
constituted a taking without just compensation and “invalidated” the
permit denial. The trial court remanded the matter to SJRWMD Governing
Board pursuant to Section 373.617, Florida Statutes, for the Governing
Board to consider the three alternatives as set forth in Section
373.617(3). The statute offers three alternatives: (1) agree to issue
the permit; (2) agree to pay monetary damages; or (3) agree to modify
its decision to avoid a taking. According to the statute, upon
selection of one of the three choices, SJRWMD is to submit a proposed
order to the trial court of its agreed-upon action within 90 days. The
trial court is then to enter a final order approving the proposed
order if the trial court determines the proposed action obviates the
taking.
SJRWMD appealed the trial court's decision, which was
titled "Final Judgment". Koontz moved to dismiss the appeal asserting
the judgment was not final since further judicial labor by the trial
court was contemplated by the judgment and Section 373.617, F.S. After
initially denying the motion and after the case was completely
briefed, the Fifth DCA granted Koontz’s motion to dismiss, concluding
the Court lacked jurisdiction because the judgment was not a final
order. The Court held the judgment contemplated further judicial labor
by virtue of the remand to SJRWMD under Section 373.617(3).
As a postscript, the SJRWMD Governing Board, on remand,
agreed to issue the permit for the Koontz development as originally
proposed, subject to appeal of the taking issue. At a hearing on the
Governing Board’s proposed action, the trial court orally ruled that
the revised permitting decision was not a taking. The parties are
awaiting entry of a written Final Judgment.
Miscellaneous:
Interagency Agreement:
In May 2004, the SJRWMD Governing Board issued a
system-wide consumptive use permit to the Orlando Utilities Commission
(OUC) for OUC’s wellfields that are located in the SJRWMD and SFWMD
within Orange County. SJRWMD’s authority to issue a CUP for that
portion of OUC’s wellfield system located in SFWMD derived from a
delegation included in an interagency agreement between SJRWMD and
SFWMD.
Section 373.046(6), F.S., authorizes such interagency agreements
when the geographic area of a project crosses water management
districts. The two districts may designate which district will
undertake permitting. The permit application is reviewed pursuant to
the rules of the designated district. An amendment to Section
373.2295 (Interdistrict transfers of groundwater) in 2003 removed
interdistrict transfers within the same county from most of the
permitting procedures contained in that statutory section.
Patrick W. Krechowski is an Assistant General Counsel to the St. Johns
River Water Management District
|