On September 30, 2005, the United States District Court
for the Southern District of Florida (Court) issued
an Order on the merits in response to Cross Motions
for Summary Judgment in the case of Florida
Wildlife Federation v. U.S. Army Corps of Eng’rs,
No. 05-CV-80339, 18 Fla. L. Weekly Fed. D1001 (S.D.
Fla. Sept. 30, 2005) (Order on Summary Judgment).
The Order on Summary Judgment concluded that the
Army Corps of Engineers (Corps) violated the
National Environmental Policy Act (NEPA) by issuing
a permit to Palm Beach County (County) for the
Scripps Research Institute (Scripps) at the
County-owned Mecca Farms site without adequate
environmental review. In summary, the Court did not
find that the project was unpermittable, but
instead, concluded that additional evaluation was
necessary. This article discusses the Order on
Summary Judgment and the subsequent Order on
Remedies. [Florida Wildlife Federation v. U.S.
Army Corps of Eng’rs, No. 05-CV-80339, 19 Fla.
L. Weekly Fed. D44 (S.D. Fla. Nov. 10, 2005) (Order
on Remedies).
The
entire Scripps site is 1,919 acres in size; the
challenged permit was for a 535-acre portion of the
site. There is a system of ditches on the property
which are connected to a tributary of the Northwest
Fork of the Loxahatchee River. These ditches are,
therefore, considered Waters of the United States.
The Complaint filed by the Florida Wildlife
Federation and Sierra Club, Inc. (Plaintiffs)
alleged that the Corps acted arbitrarily and
capriciously by failing to consider the impact of
the entire 1,919 Scripps development; the Corps
segmented the project unlawfully to avoid a finding
of significance; the Corps’ environmental analysis
failed to consider all environmental concerns; and,
the Corps performed an inconsistent and insufficient
alternatives analysis. (Order on Summary Judgment,
p. 19) The Plaintiffs alleged that the Corps’
action violated NEPA; the Clean Water Act and the
Rivers and Harbors Act of 1899. The Plaintiffs
requested that the Court find that the permit issued
by the Corps was invalid and require the Corps to
prepare an Environmental Impact Statement (EIS) that
addressed the entire scope of the planned
development.
The
County asked that the Court find that the 535 acres
could be reviewed independently from the remaining
acres as well as any other potential impacts because
the 535-acre project had independent utility and
could be constructed solely without the need for the
remaining development. (Order on Summary Judgment,
p. 8)
The
Corps argued that the proposed project “would not
have a significant impact on the environment”
because the issuance of the Section 404 permit was a
“federal” action, but not necessarily a “major”
federal action, triggering the requirements of NEPA.
(Order on Summary Judgment, pp. 19, 20) Because the
Corps found no significant impact, the Corps did not
prepare an EIS and, instead, issued the permit. The
Corps also determined that the public hearing
requested in comments was not needed because all the
issues raised during the comment process had been
identified and resolved. The finding of no
significant impact and the decision not to prepare
an EIS was a final administrative decision
reviewable under the Administrative Procedures Act.
(Order on Summary Judgment, p. 11)
The
Corps argued that it had properly limited the scope
of its analysis to the aspects of the project over
which it had sufficient “control and responsibility”
to warrant federal review, in this case the 535
acres. The Corps further argued that the project
had independent utility because it would be
constructed without the need for the construction of
other projects in the project area. The Corps
acknowledged that it was aware of plans for future
development; that it would have jurisdiction over
the next phases of development; and, that it
anticipated applications for those future phases.
(Order on Summary Judgment, p. 22)
The
Court found that the filling of wetlands in the
ditches on the 535 acres was not discrete because
the ditches ran throughout the site. (Order on
Summary Judgment, p. 23) The “anti-segmentation
rule,” which holds that an agency cannot evade its
responsibilities under NEPA by artificially dividing
a major federal action into smaller components, was
applied to find no significant impact. (Order on
Summary Judgment, p. 23) The Order states that
segmentation occurred in two ways: first, when the
Corps limited its analysis to the 535 acres instead
of the entire 1,919-acre site and, second, when the
Corps authorized the extension of PGA Blvd. without
considering its projected connection to the Bee Line
Highway across wetlands. The Court found that
ending an extension of PGA Blvd. in a cul-de-sac, as
was proposed in the project design, was not a
logical terminus. The Order stated that permitting
the first part of the road without considering the
future effects was an arbitrary and capricious
determination that the project did not have any
significant environmental impacts. (Order on
Summary Judgment, p. 30)
The
Corps argued that it only needed to consider the
effects of cumulative actions that were already
proposed. It declined to consider planned future
development. The Corps stated that it would
evaluate the cumulative impacts of future potential
development when applications are received. (Order
on Summary Judgment, p. 49) The Court did not agree
with this approach and found that the future
development of at least the remainder of Mecca Farms
was being actively pursued and thus was not
speculative. The 1,919 acre site was not a series
of projects but, instead, an integrated whole.
Although the project had independent utility, it was
not intended to stand alone. (Order on Summary
Judgment, p. 52)
The
Corps’ rules require an analysis of alternative
sites. In this case, five alternative locations
were considered. The Corps considered the economic
development of the entire 1,919 acre project in its
alternatives analysis, not just the 535 acres in
Phase I. The Court found that alternatives and
benefits analysis did not match the scope of the
impact analysis. The information the County
submitted for the alternatives analysis stated that
other identified sites did not meet the size
requirements. The Court found that the scope of the
alternatives analysis incorporated consideration of
the entire project rather than limiting it to the
scope of the proposal before the Corps, which was
improper. The Court further found that since the
alternatives analysis was not properly limited in
scope, the Court could not ascertain whether
environmental considerations were adequately
addressed. (Order on Summary Judgment, pp. 57-59)
After
ruling in the Plaintiffs’ favor on the Motion for
Summary Judgment, the Court directed the parties to
file memoranda on remedies. On November 10, 2005,
the Court entered its ruling on those remedies. [Florida
Wildlife Federation v. U.S. Army Corps of Eng’rs,
18 Fla. L. Weekly Fed. D1015 (S.D. Fla. Nov. 10,
2005)] The Plaintiffs’ Memorandum on Remedies
requested that the Court set aside the Corps’
permit; order the Corps to perform an EIS that took
into account the effects of all reasonably
foreseeable impacts identified in the Court’s
September 30, 2005, Order or the administrative
record; and enjoin all development of the project
pending the completion of the environmental review.
The Corps, the County and Scripps asked the Court to
remand the matter to the Corps for further
consideration in light of the Court’s Order and to
take no further action.
The
Corps, the County and Scripps contended that the
Court did not have jurisdiction to enjoin the County
or Scripps because the action was against the Corps
only for violations of NEPA, a federal statute that
only requires compliance by the Corps. The County
and Scripps were not named as defendants in the case
and were heard only as Amici Curiae during
the merit phase of the litigation and were only
granted intervener status during the remedial
phase. (Order on Remedies, p. 12)
While
injunctions are generally only issued against a
party, a court has the power to enjoin third parties
but only under limited circumstances and when
necessary to ensure the effectiveness of its
orders. [28 U.S.C. s1651(a)] (Order on Remedies, p.
13) In this case, the Court found that while no
cause of action had been asserted against the County
or Scripps, injunctive relief was necessary in order
to give effect to the Court’s September 30, 2005,
ruling. (Order on Remedies, p. 15) The Court found
that the Plaintiffs had suffered irreparable injury,
not just the harm from the direct dredging and
filling of wetlands, but also the harm that arose
from allowing the Corps to permit a large
“growth-inducing” development in an environmentally
sensitive area without first considering all the
“reasonably foreseeable indirect and cumulative
effects of such action.” (Order on Remedies, p.
17)
The
Court found that if construction was not enjoined
“these as yet unexamined effects would begin to take
place and no amount of subsequent environmental
analysis would undo them.” (Order on Remedies, p.
17) Since injunctive relief is not mandatory under
NEPA, the Court balanced various equitable factors
to determine whether an injunction was appropriate
in this instance. An injunction may be granted if
the moving party has prevailed on the merits and
demonstrated that irreparable injury will be
suffered unless the injunction issues; that the
threatened injury to the movant outweighs any damage
the injunction may cause to the opposing party; and
the issuance of an injunction would not be adverse
to the public interest. Once this has been shown,
then the Plaintiffs have the burden of demonstrating
that the harm from continued construction outweighed
the harm to the party that would be enjoined.
The
Court found that equity weighed in the County’s and
Scripps’ favor as to certain components of the
construction plan and therefore elected to exclude
those components from the scope of the injunction.
First, the jurisdictional wetlands on the 40-acre
site where the 3 buildings will be constructed were
filled before the action was filed. Second, when
Scripps received the land, Scripps was not itself
required to obtain any federal permits to initiate
construction. Third, Scripps has a $5 million gift
which requires permanent facilities be constructed
on the 44-acre site within the current construction
schedule. (Order on Remedies, p. 24)
Judge
Middlebrooks found that the facts weighed against
enjoining Scripps’ construction of its 3 buildings
and that this limited construction would not be
adverse to the public interest. The Court found
that carefully tailored injunctive relief could
allow some construction while still ensuring a “full
and fair environmental review.” (Order on Remedies,
p. 24) All construction was enjoined with the
exception of the 3 buildings, the completion of
Seminole Pratt-Whitney Road which was more than
forty percent complete, the construction of a
pipeline which will also serve other facilities, and
mitigation designed to compensate for the harm
caused by dredging and filling of jurisdictional
wetlands. Finally, the matter was remanded to the
Corps for reconsideration in light of the Court’s
September 30, 2005, Order.