ELULS.orgThe Environmental and Land Use Law Section of The Florida Bar
Section Reporter

July 2007

COLUMNS  
     

ELULS.org  DEP Update
  Kelly Samek & Amanda G. Bush

      

ACF Update
On March 28, the U.S. Army Corps of Engineers issued a public notice advising that its Mobile District had completed an Environmental Assessment and Finding of No Significant Impact for modifications to the Woodruff Dam Interim Operations Plan describing minimum releases and maximum fall rates for releases to the Apalachicola River from the dam. Florida sent a 60-Day Notice of Intent to Sue to the Corps and the U. S. Fish and Wildlife Service for violations of the Endangered Species Act in the operation of Woodruff Dam under the Modified Interim Operation Plan.

The federal panel on multidistrict litigation entered an order transferring part of State of Alabama v. U.S. Army Corps of Engineers, et al., 90-CV-1331-Bowdre (N.D. Ala.), as well as Southeastern Federal Power Customers, Inc. v. Luis Caldera, et al., 1:00-CV-02975-Jackson (D.C. Cir.), State of Florida v. U.S. Fish and Wildlife Service, et al., pending in the Northern District of Florida, and State of Georgia v. U.S. Army Corps of Engineers, et. al., pending in the Northern District of Georgia, to the Middle District of Florida. (The remainder of State of Alabama v. U.S. Army Corps of Engineers, et al. concerning the ACT Basin will continue in the Alabama district court without Florida’s participation.) The Panel found that the four cases involve common questions concerning the conduct of the Corps regarding the flow of water in the ACF basin. The Panel recognized that the cases involve parties and interests located in the 11th Circuit Court of Appeals and transferred the cases to the middle district so that the 11th Circuit would retain appeal jurisdiction. The panel selected Judge Paul Magnuson of the District of Minnesota to serve as judge for the consolidated cases, citing his expeditious handling of the Missouri River litigation.

S-2, 3, and 4 Litigation, Case No. 02-80309-CIV-Altonaga/Turnoff: On March 6, the Florida Wildlife Federation filed a motion to join Secretary Sole into the federal S-2, 3, and 4 case as an involuntary plaintiff. The Court has previously ruled that the SFWMD was in violation of the Clean Water Act for failing to obtain NPDES permits for the 3 pump structures that periodically back pump into Lake Okeechobee. The case is now in the remedy phase. The Department objected to the joinder.

In Re: Florida Power & Light Company, FPL Glades Power Park, Power Plant Siting Application No. PA 06-49, DOAH Case No. 06-005334EPP: This is an application for the construction and operation of a new 1,960-megawatt coal fired power plant in Glades County pursuant to the Power Plant Siting Act. The ALJ has scheduled a land use hearing on those petitions to be held in Glades County on June 5.

FPL Rule Challenge (CAIR), Case No. 3D07-840, DOAH Case No. 06-2871RP: On March 1, a DOAH final order was entered finding that the Clean Air Interstate Rule is valid. The ALJ found that the Department did not exceed its grant of rulemaking authority; did not enlarge, modify, or contravene the law being implemented; was neither arbitrary nor capricious; did not impose excess regulatory costs on a regulated person; and did not violate the requirements for issuing a statement of estimated regulatory cost. The challenged provisions of the Department’s CAIR were exactly the same provisions adopted by EPA in its model CAIR rule (model rule was developed for states to use to ensure consistency among states participating in the cap-and-trade program) and in the EPA federal implementation plan. Subsequent to the final order, the challenged provisions of the CAIR rule were filed with the Secretary of State and became effective April 2. On March 30, Florida Power & Light appealed the final order in the Third District Court of Appeals.

Rule 62-730.186: On February 22, the Environmental Regulation Commission approved adoption of the Universal Pharmaceutical Waste Rule. This rulemaking is the product of work by several affected constituencies including medical facilities, federal facilities, hazardous waste transporters, reverse distributors, and the Department of Health. Florida is the second state in the nation to allow hazardous pharmaceutical waste to be managed using the less stringent regulations applicable to universal waste. The rule became effective April 22, 2007.

Renewable Energy Technologies and Energy Efficiency Rule: On February 9, the Florida Energy Office published a notice of proposed rulemaking for a new rule chapter, 62-16, to implement the provisions of the 2006 Florida Energy Act (2006 Senate Bill 888). The proposed rule will provide for application requirements, ranking of applications, and will administer the awarding of grants under the Renewable Energy Technologies Grants Program; develop rebate applications and administer the issuance of rebates for the Solar Energy Systems Incentives Program; and implement corporate tax incentives provided for renewable energy technologies. A public hearing was held on April 17 to accept comments on the rule.

Citation Correction from April 2007 publication: St Johns Riverkeeper, et al v. U.S. EPA was incorrectly cited to 3:04-CV-699-J-32MCR. The correct citation for the case published in the update is 4:06-CV-00332-SPM-WCS (N.D. Fla.).


 

ELULS.orgCopyright 2008, The Environmental and Land Use Law Section of The Florida Bar