| (Ed. Note: footnotes and hyperlinks will be added soon)
Originally, the Department
of Environmental Protection ("DEP" or "Department") handled both wetland
resource ("dredge and fill" or "WR") and Management and Storage of Surface
Waters ("MSSW") permitting. It was thereafter delegated by the State
to four of the five Water Management Districts. DEP retained permitting
within the Northwest Florida Water Management District. In the early
90s, there began a realization that there was a lot of overlap between
the dredge and fill permitting program implementation by DEP and the MSSW
implemented by the water management districts. In an effort to streamline,
in approximately 1992, DEP implemented delegation agreements with some
of the water management districts. Pursuant to these agreements,
an applicant could either go to the District or the Department, depending
on the kind of activity that was proposed, to get both an MSSW and a dredge
and fill permit. Certain kinds of activities were regulated by the water
management districts and certain kinds by the Department. DEP maintained
an oversight role, and the rules with respect to dredge and fill permits
remained the rules of the Department. Eventually, further streamlining
was mandated by statute.
Chapter
93-213, Laws of Florida, contains the Florida Environmental Reorganization
Act of 1993. It consolidated the dredge and fill permit, previously
provided for in Chapter 403, Florida Statutes, and MSSW permit, previously
provided for in Chapter 373, Florida Statutes, and their permitting criteria,
into a single permitting program, which resulted in the creation of the
Environmental Resource Permit ("ERP"). Part IV of Chapter 373, Florida
Statutes, now contemplates a comprehensive permit system and combines the
two. The new permit is issued by one entity, rather than multiple
entities.
There
is a grandfathering provision that allows persons who submitted applications
on or before June 15, 1994, to have their permits processed under rules
adopted prior to those adopted pursuant to the new law. Section 373.414(11)
- (16), Fla. Stat. (1997). Practitioners may still yet find
themselves litigating under the former statutory and rule schemes and may
find the discussion of those schemes contained herein useful in that respect.
However, more importantly, the case law relating to the former dredge and
fill and MSSW permits developed over the years remains persuasive with
respect to secondary impacts analysis under the ERP regulatory program.
Subsequent
to passage of the ERP legislation, DEP and the water management districts
developed new rules to implement the ERP. One component of those
rules is a codification of the required secondary impacts analysis.
Ostensibly, the intention was to codify the analysis which had been implemented
through interpretation of the doctrine of secondary impacts as it had developed
through case law.
Closer scrutiny
of the ERP rules, however, reveals differences between the rules and the
judicially developed doctrine. However, the case law which has developed
with respect to WR and MSSW permitting certainly continues to be relevant
and highly persuasive with respect to ERP permits. The following
is a discussion of secondary impacts analysis under State of Florida law,
and to a lesser extent cumulative impacts, a concept which is often lumped
in with, or confused with, concept of secondary impacts.
SECONDARY IMPACTS ANALYSIS IN
WETLAND RESOURCE AND MANAGEMENT AND STORAGE OF SURFACE
WATERS PERMITTING AND THE TRANSITION TO ENVIRONMENTAL RESOURCE PERMITTING
Dredge and
fill permits and MSSW permits were permitting tools prior to 1993.
See Chapters 403 and 373, Fla. Stat. (1991 and 1992 supp.). Both
permits had a required secondary impacts analysis. Both were replaced
by the Environmental Resource permit (ERP) pursuant to 93-213, Laws of
Florida. However the analysis involved in dredge and fill and MSSW
permitting remains highly persuasive in the ERP permitting context because
of an expressed legislative intent to rely primarily on existing rules
of DEP and the districts in implementing the ERP program. §373.414(9),
Fla. Stat. (1997).
The secondary
impact analysis was first developed in the context of dredge and fill permitting
as a judicially created doctrine in the case of del Campo v. State Department
of Environmental Regulation, 452 So.2d 1004 (Fla. 1st DCA 1984).
There the court instructed the Department of Environmental Regulation (one
of the predecessors of the current Department of Environmental Protection),
in reviewing a dredge and fill permit for a bridge, to consider not only
the wetland impacts of the bridge construction but also the potential impacts
on the island to be bridged.
Since the
del Campo case, DER, and its successor DEP, have been considering secondary
impacts in dredge and fill permitting, and the courts have continued to
refine how the concept of secondary impacts should be applied. An
important case to consider when evaluating secondary impacts is Conservancy,
Inc. v. A. Vernon Allen Builder, 580 So.2d 772 (Fla. 1st DCA 1994).
In that case, the court indicated:
[F]or purposes of applying and balancing
the statutory public interest criteria in Wetland Resource ("WR") and Management
and Storage of Surface Waters ("MSSW") §403.918 [DERs policy is ]
to look at the actual jurisdictional area to be dredged and filled, and
any other relevant activities that are very closely linked or causally
related to the proposed dredging and filling. (Emphasis added)
As for MSSW
permitting, case law which existed at the time of the enactment of Chapter
93-213, Laws of Florida, had established that water management districts
must also consider secondary impacts when issuing MSSW permits under Chapter
373, Part IV, Florida Statutes (1991 and 1992 supp.). The requirement
was first established as a requirement in an order of the Governor and
Cabinet, acting as the Land and Water Adjudicatory Commission (FLWAC),
reviewing a final order of the St. Johns River Water Management District.
Sierra Club v. St. Johns River Water Management District and the Department
of Transportation, ER FALR 92-131 (Case No. RFR-92-001, July 22, 1992).
FLWAC indicated that the Florida Legislature had, in effect, copied into
Chapter 373, Florida Statutes, the identical policy statements from Section
403.021, Florida Statutes, relating to dredge and fill permits. FLWAC
then indicated that [t]he consideration of impacts of other relevant activities
that are very closely linked or causally related to the permitted activity
is essentially a secondary impact analysis. Id. at 3. Further,
FLWAC ordered the water management districts to develop rules providing
for secondary impact analysis as part of their MSSW permitting evaluation.
Development of the ERP rules eliminated the need for the water management
districts to develop secondary impact rules for MSSW permits distinct from,
or identical to, DEP dredge and fill requirements.
Burden of Proof in Permitting
Cases
In any permitting
case, the applicant has the burden of proof to demonstrate entitlement,
by a preponderance of the evidence, to the sought permits. FDOT v.
JWC Company, Inc., 396 So.2d 778 (Fla. 1st DCA 1981). This includes
the burden to show that there will be no adverse cumulative or secondary
impacts. Concerned Citizens League of America, Inc. et al. v. IMC
Fertilizer, Inc. and Department of Environmental Protection, 89 ER FALR
41 (Final Order issued March 29, 1989).
Wetland Resource Permitting Criteria
The pre-ERP
WRM program regulates activities taking place within the wetland jurisdiction
of the DEP -- i.e., within the landward extent of waters of the state --
as delineated in accordance with the pre-ERP rules of the DEP. Section
373.414(12), Fla. Stat.; Rule 62-312.090, F.A.C. Issuance of a WRM
permit is based upon an applicant's providing reasonable assurances that
the project will comply with the permit criteria, including the public
interest test, contained in Section 403.918, Florida Statutes (1991 and
1992 supp.), and rules promulgated thereunder.
Further,
in order to determine whether an applicant has met its burden of proof
and demonstrated entitlement to a dredge and fill permit, Rule 62-4.070,
Florida Administrative Code established a standard of review that the applicant
provide reasonable assurance that the proposed activity will not cause
pollution in contravention of Department standards or rules. 62-4.070,
F.A.C. Reasonable assurance contemplates . . . a substantial likelihood
that the project will be successfully implemented. Metro Dade County
v. Coscan Florida, Inc., 609 So.2d 644, 648 (Fla. 3d DCA 1992).
The public
interest test set forth in Section 403.918, Florida Statutes (1991 and
1992 supp.), is as follows:
(a) In determining whether a project
is not contrary to the public interest, or is clearly in the public interest,
the department [or a water management district when the authority is delegated]
shall consider and balance the following criteria:
1. Whether the project will adversely
affect the public health, safety, or welfare or the property of others;
2. Whether the project will adversely
affect the conservation of fish and wildlife, including endangered or threatened
species, or their habitats;
3. Whether the project will adversely
affect navigation or the flow of water, cause harmful erosion or shoaling;
4. Whether the project will
adversely affect the fishing or recreational values or marine productivity
in the vicinity of the project;
5. Whether the project will be of
a temporary or permanent nature;
6. Whether the project will adversely
affect or will enhance significant historical and archaeological resources
under the provisions of §267.061; and
7. The current condition and relative
value of functions being performed by areas affected by the proposed activity.
The balancing
of the public interest criteria is ultimately a conclusion of law for which
the permitting entity has the final responsibility and authority to decide.
1800 Atlantic Developers v. Department of Environmental Regulation, 552
So.2d 946 (Fla. 1st DCA 1989); rev. den., 562 So.2d 345 (Fla. 1990).
Under the
case law interpreting the public interest test, the permitting entity cannot
consider non-environmental factors under the "public health, safety, or
welfare or property of others" prong of the public interest test.
Miller v. Department of Environmental Regulation, 504 So.2d 1325 (Fla.
1st DCA 1987)(property of others); Taylor v. Cedar Key Sewage District,
590 So.2d 481 (Fla. 1st DCA 1991)(compliance with land use restrictions);
Grove Isle Ltd. v. Department of Environmental Regulation, 454 So.2d 571
(Fla. 1st DCA 1984)(limits public interest analysis to pollution); Council
of the Lower Keys v. Charlie Toppino & Sons, Inc., 429 So.2d 67 (Fla.
3d DCA 1983)(excludes consideration of zoning, land use and long range
development plans). There is, however, some contrary case law with
respect to this matter. See e.g. VanWaggoner v. Department of Transportation
and Department of Environmental Protection, 96 ER FALR 78 (Final Order
dated May 14, 1996), affd Save Anna Maria v. Dept. of Transportation,
700 So. 2d 113 (Fla. 2d DCA 1997) (a fairly recent case with internal contradictions
on the issue of consideration of non-environmental factors. The consideration
of non-environmental safety factors was allowed in this case.)
Specific
rules for wetland resource permits were contained in Chapter 62-302, Florida
Administrative Code relating to water quality standards, and in Chapter
62-312, Florida Administrative Code, relating to dredge and fill permitting,
as that rule existing prior to the ERP rules.
Secondary and Cumulative Impacts
Analysis Under Wetland Resource Permitting Criteria
In determining
whether a proposed project satisfies the requirements of law, the doctrines
of "secondary" and "cumulative" impacts are applied to dredge and fill
permitting. See Conservancy, Inc. v. A. Vernon Alan Builder, 580
So.2d 772 (Fla. 1st DCA 1991)(with regard to secondary impacts the court
said, "such evidence would be highly relevant to the consideration of whether
the applicant has carried its burden of giving reasonable assurances under
section 403.918 that water quality standards will not be violated and the
project is not contrary to the public interest [or clearly in the public
interest]."), review denied, 591 So.2d 631 (Fla. 1991). Secondary
impacts are those indirect impacts outside the project area, whereas cumulative
impacts are those created by the cumulative effects of existing or future
projects.
The cumulative
impacts' test was codified in Section 403.919, Florida Statutes (1991),
and requires the permitting entity to consider the following:
(a) The impact of the project for
which the permit is sought.
(b) The impact of projects which
are existing or under construction or for which permits or jurisdictional
determinations have been sought.
(c) The impact of projects which
are under review, approved, or vested pursuant to §380.06, or other
projects which may reasonably be expected to be located within the jurisdictional
extent of waters, based upon land use restrictions and regulations.
Cumulative
impacts are basically those impacts that may result from the added effects
of many existing or future projects. Conservancy, 580 So.2d at 777-778.
The purpose of the cumulative impact analysis is to prevent piecemeal destruction
of the environment, Florida Power Corp. v. Department of Environmental
Regulation, 92 ER FALR 56 (Final Order issued April 1, 1992). The
term "reasonably likely" to occur does not mean that there needs to be
a permit or even a pending application. del Campo, 452 So.2d at 1006
(Smith specially concurring and dissenting in part, cited with authority
in A. Vernon Allen, 580 So.2d at 778).
Integral
to the dredge and fill permitting process is a requirement that there be
an assessment of, and mitigation for, the secondary impacts, or off-site
impacts, associated with a project. This judicially created doctrine
was first developed in the context of dredge and fill permitting in the
case of del Campo v. State Department of Environmental Regulation, 452
So.2d 1004 (Fla. 1st DCA 1984)(Hearing Officer erroneously excluded evidence
of the possible environmental impacts on an island of a proposed residential
development during hearing regarding dredge and fill permit for construction
of a bridge to the island). In that case, the Court held that when
DER was reviewing a dredge and fill permit, it had to consider not only
the wetland impacts of the bridge construction, but also the potential
impacts of development on the island to which the bridge was being built.
Since del Campo, courts have continued to discuss, refine, and develop,
the concept of secondary impacts.
It is also
clear from the DEP's decision in McCormick v. City of Jacksonville 12 FALR
960, 980 (January 22, 1990), that the agency is willing to apply a secondary
impact analysis and to consider the impacts of the total development authorized
by the proposed dredge and fill permit and those very closely linked or
causally related. This consideration is essential to the agency's
evaluation of whether the applicant has provided the requisite "reasonable
assurances" required by Section 403.918, Fla. Stat. (1991). See Conservancy,
Inc. v. A. Vernon Alan Builder, 580 So.2d 772 (Fla. 1st DCA 1991)
The Conservancy
case held that if a project facilitates development, the impacts of that
development must be considered in the secondary impacts analysis.
Conservancy, 580 So.2d at 777 (the determination of the permittability
of the project must consider its secondary impacts, or "those outside the
project area caused or enabled by the project. . . ." Conservancy,
580 So.2d at 779.) Further, under that same case, proof of a direct
causal connection is not necessary for secondary impacts to be considered.
Instead, the closeness of causality helps to determine the weight given
to a secondary impact. The Court in Conservancy quoted the Secretary
of DER as follows:
Specifically in the context of permitting
access roads and bridges, it has been the policy of the Department to consider
what will be at the end of the bridge or road. . . . Of course, if the
activities or impacts at the end of the bridge or road are remote in distance
or conceptual relationship from the dredge and fill activity, those activities
or impacts should be weighed accordingly in applying the statutory balancing
test.
Id. at 778 (emphasis added).
Thus, rather than being a condition precedent to consideration, even if
a secondary impact is not directly causally related to the project, it
must still be considered, just weighed accordingly. An applicant
has the legal duty to analyze for secondary impacts and either show reasonable
assurances that there are none or plan to mitigate for them. See
Conservancy, Inc. et al. v. A. Vernon Allen Builder, Inc. and DER, 15 FALR
292 (Final Order issued January 4, 1993)(the impacts of subsequent residential
development on the island, which were secondary impacts associated with
the construction of a subaqueous sewer line to Keewaydin Island were mitigated
by the preservation of a conservation easement on 2,270 acres).
In Pine
Island Properties, Ltd. v. DEP, (DEP Case 92-0460, May 5, 1994), 1994 WL
497287, a dredge and fill permit was denied based upon the secondary and
cumulative impacts from boat traffic. Although not part of the permit
application, in that case the construction of boat docks in the canal was
determined to be a secondary impact that could be reasonably be expected
to occur as a result of the issuing of a permit for the proposed activity.
In that case, the applicant failed to provide reasonable assurance that
boats crossing the area between the canal and the sound will not cause
violations of water quality, including turbidity and loss of diversity,
and loss of wetland resources, seagrass beds. Hence the permit was
denied.
Water pollution
from septic tank effluent is yet another secondary impact of dredge and
fill permits that must be evaluated. Cape Cave Corporation v. Department
of Environmental Regulation, 489 So.2d 1309 (Fla. 1st DCA 1987), which
affirmed Environmental Confederation of Southwest Florida, Inc. v. Cape
Cave Corporation and DER, 8 FALR 317 (Final Order DER 1985). While
Chapter 381, Florida Statutes, delegates permitting authority over individual
septic tanks elsewhere, DEP retains authority "to consider septic tank
impacts on water quality when such impacts are being reviewed in conjunction
with a Department permit." See also, Taylor v. Cedar Key Special
Water and Sewer District and Department of Environmental Regulation, 91
ER FALR 15 (Final Order issued December 18, 1990).
Applicants
have the responsibility to assess and propose mitigation for any secondary
impacts associated with a project prior to obtaining a permit. This
must be done either in its permit application or at a hearing in order
to provide reasonable assurances that a project will meet all applicable
standards and criteria. Evaluation of secondary impacts cannot be
put off to a later date. Metropolitan Dade County v. Coscan Florida,
Inc and Department of Environmental Regulation, 609 So.2d 644 (Fla. 3d
DCA 1992); Rudloe and Gulf Specimen Co. Inc. v. Dickerson Bayshore, Inc.
and Department of Environmental Regulation, 10 FALR 3426 (Final Order issued
June 9, 1988); Concerned Citizens, supra. at 5.
In Coscan,
the Court reversed the Hearing Officer and DER, which had recommended approval
of a dredge and fill permit to construct a marina in phases conditioned
upon the monitoring of water quality prior to each phase. The Court
said, "We do not think that the statute [Section 403.918, Fla. Stat. (1987)]
allows the agency to proceed without an analysis, in advance of (1) the
likely effects of the project and (2) the question whether the applicant
has provided reasonable assurances that water quality standards will be
met." (emphasis added) Id. at 647. It went on to state:
The statute is prohibitory:
it requires reasonable assurances before the project is started that water
quality in the affected area will not be violated. It is not within
the hearing officer's province to allow a developer to proceed with a project
of this magnitude with no idea as to what the effect on water quality will
be. (emphasis added)
Id.
MSSW Permitting Criteria and Cumulative
and Secondary Impacts Requirements
Chapter
373, Florida Statutes, concerns water resources and governs the management
and storage of surface waters. Part IV of the chapter is of particular
importance. That chapter, as it existed prior to the statutory reform
of the permitting program, and the implementing rules of the water management
districts governed issuance of MSSW permits. Section 373.413, Florida
Statutes required that the applicant provide reasonable assurances that
the project complies with the statute and rules and "not be harmful to
the water resources of its district." Different water management
districts had different sets of rules in the Florida Administrative Code
implementing this statutory provision.
The secondary
impacts analysis is also applicable to the MSSW permitting process.
The secondary impacts' analysis for surface water management permits, as
previously discussed, was first established as a requirement in an Order
of the Governor in Cabinet sitting as the Florida Land and Water Adjudicatory
Commission ("FLWAC") and reviewing a Final Order of the St. Johns Water
Management District.
Under
Chapter 373 F.S., the only express requirement for considering the cumulative
and secondary impacts in management and storage of surface water permitting
concerned small isolated wetlands that are not within DEP's dredge and
fill jurisdiction. However, FLWAC, citing Booker Creek Preservation,
Inc. v. S.W. Fla. Water Mgmt. District, 534 So.2d 419 (FLA. 5th DCA 1988),
and Department of Environmental Regulation v. Goldring, 477 So.2d 532 (Fla.
1985), noted that statutes enacted to protect the environment (including
Chapter 373) must be liberally construed. FLWAC cites Perry v. City
of Jacksonville (FLWAC Case No. RFR-91-001, Feb. 14, 1990) as representing
the proposition that a review of MSSW permits should consider the impacts
on habitats of wetland dependent upland species. In addition, the
FLWAC encouraged the passage of an amendment, later adopted by the St.
John's River Water Management District, expanding review from impacts to
aquatic and wetland dependent species, to impacts to all wildlife.
FLWAC recognized
that cumulative impact analysis is necessary to "prevent piecemeal destruction
of the environment." FLWAC went on to say that "without the ability
to consider the long term impacts of a project in combination with past
and reasonably likely similar projects in the area, the MSSW permitting
agency would be helpless to prevent the gradual elimination of environmental
resources through MSSW permits." Therefore, FLWAC held that "Chapter
373, F.S., authorizes the MSSW permitting agency to consider and evaluate
cumulative and secondary impacts for both isolated and non-isolated wetlands."
Furthermore, the Commission directed the District to amend its MSSW rules
to consider cumulative and secondary impacts for both isolated and non-isolated
wetlands. The FLWAC position entrenches the notion that effective
environmental regulation requires an expansive and forward-looking view
of effects on an integrated ecosystem. McCormick v. City of Jacksonville,
12 FALR 960 (January 22, 1990).
Sierra Club
also represents a movement toward a broader and more inclusive view of
the effects of environmental regulation. FLWAC rejected the idea
that the impact of individual components of a larger project should be
reviewed independently. By unifying the decision making process,
a more comprehensive view of the effects of a project may be taken.
SECONDARY IMPACTS ANALYSIS IN
ENVIRONMENTAL RESOURCE PERMITTING
The 1993
legislation effectively repealed and transferred relevant portions of the
Warren S. Henderson Wetland Protection Act (403.91-403.929, Florida Statutes),
moving them from Chapter 403, Florida Statutes, to Chapter 373, Part IV,
Florida Statutes. Most notably, Sections 403.918 (the public interest
test) and 403.919 (cumulative impact provision), Florida Statutes, have
been integrated into Section 373.414, Florida Statutes. It provided
that a single entity should issue a single permit for construction activities
which have been historically regulated under individual dredge and fill,
management and storage of surface water, stormwater and mangrove alteration
permitting programs. The sovereign submerged lands program has been
integrated as well. Depending on the activity to be conducted, an ERP permit
must be obtained from either the DEP or a water management district pursuant
to operating agreements.
The cumulative
impact provision previously in Section 403.919, Florida Statutes was modified
and transferred to Section 373.414(8), Florida Statutes . The revised
cumulative impact analysis was limited to projects and impacts in the same
drainage basin and based on the local government's adopted comprehensive
plan. The statute did much more than described herein, but the merger
of the dredge and fill and MSSW permitting programs and the secondary impacts
analysis are most relevant for our discussion here.
The statute
required that the Florida Environmental Reorganization Act be implemented
pursuant to rule, which would merge existing programs no later than July
1, 1994. Pursuant to the Act, the 1994 Legislature adopted a state-wide
wetlands delineation rule which became effective July 1, 1994. Other
implementation was delayed during the summer of 1994, when the various
proposed ERP rules approved by the Environmental Regulation Commission
and water management district governing boards were challenged by the Florida
Electric Power Coordinating Group, Florida Chamber of Commerce, Florida
Developers and Florida Home Builders Association in DOAH Case No. 94-2722RU;
Gerald Ward, in DOAH Case No. 94-2930RP; Florida Phosphate Council, in
DOAH Case No. 94-2935RP; and St. Joe Paper Company and Florida Waste Coast
Industries, in DOAH Case No. 94-2936RP.
The
Florida Environmental Reorganization Act idea was intended to streamline
the process but maintain the substance. The statute indicates "[t]his
section shall not be construed to diminish the jurisdiction or authority
granted prior to the effective dates of this act . . . ." §373.414(7),
Fla. Stat. (1997) Petitioners argued that the proposed ERP rule was
an effort by DEP and the districts to increase jurisdiction. Environmental
groups argued DEP and the districts were receding from existing authority.
Annual Environmental and Land Use Law Update, August 1995, Wetlands/MSSW/ERP
Update by Daniel H. Thompson et al at 8.4.
After litigation
in the fall and winter, while still awaiting the final order of the hearing
officer, most of the parties entered into a settlement agreement.
Id. at 8.4. Among the subjects of that settlement was secondary impacts.
Later, in April, the ERC and WMD Governing Boards approved the changes
to the proposed ERP rules essentially as contained in the settlement.
Id. at 8.4. A few non-settlors continued to litigate the revised
version in a rule challenge. The challenge was decided in favor of
the Department, and the decision was affirmed on appeal in May of 1996,
although the program became effective on October 3, 1995.
In order
to receive an ERP, an applicant must provide reasonable assurance that
the permitting criteria provided in the ERP rules and the statute are met.
The rule criteria are found in rules 40X-4.301 and .302, Florida Administrative
Code. ERP permits are issued on an activity based split with
DEP. DEP has adopted its own rules and has adopted by reference portions
of the districts' rules.
The
ERP rules adopt by reference either an Applicant's Handbook (AH) or Basis
of Review (BOR) (look for BORs when you have cases grandfathered as well).
These documents explain in greater depth what will be considered during
review of a permit application, and what an applicant must do to meet the
permitting criteria.
The ERP rules include changes to secondary impact analysis. The major
change deals with how the permitting authorities consider impacts to listed
species and the geographic scope of consideration. In the ERP program,
the secondary impact review provision was ostensibly an attempt to harmonize
differences between the DEP and water management district approaches to
this review. Only aquatic or wetland dependent species will be considered
under the ERP review. The ERP also now includes the buffer concept.
There is now a presumption that habitat conditions will not be affected
when certain buffer requirements are met.
Another
identifiable departure from previous secondary impacts doctrine is the
adoption of the "but for" test. The ERP rules seem to limit the impacts
considered under the secondary impacts analysis to impacts that would not
occur "but for" the proposed project. See e.g. SJRWMD's Handbook
for ERP Permits at 12.2.7(d). This is a new test not previously enunciated
in case law except for with respect to the recent case relating to the
widening of U.S.1 in the Florida Keys. It has, however, been argued
that this "but for" requirement already existed in the secondary impacts
doctrine.
The Proposed Widening of U.S.
1 in the Florida Keys
The following
is a discussion of the proposed widening of U.S. 1 in the Florida Keys.
This author is an attorney for parties to the appeal of the order issuing
the state permits necessary to widen the road. It is included, because
the case raises some interesting and cutting-edge issues regarding the
scope of secondary impacts review. The discussion represents our
position that the project is not permittable and that the Final Order departed
from existing law.
The
Florida Department of Transportation ("FDOT") applied to the South Florida
Water Management District ("SFWMD") for the permits necessary to widen
20.4 miles of two-lane U.S. 1 in southern Dade and northern Monroe Counties
to a road on a four-lane road bed, with a four-lane embankment, which has
variously three and four lanes of pavement along the project (much of the
20.4 mile road would be four lanes). The permits necessary to execute
the project are an MSSW permit, a Wetland Resource permit, and a modification
to a Right of Way/Occupancy permit ("ROW"). Pursuant to the previously
discussed grandfathering provision, FDOT requested that the permits be
reviewed under the pre-ERP statutory framework.
The SFWMD
issued "Staff Reports" on October 24, 1995, with an addendum dated November
3, 1995. The SFWMD staff recommended issuance of the permits subject
to general and special conditions. Based on the Staff Reports,
SFWMD issued its notice of intent to issue the permits with conditions.
Thereafter,
1000 Friends of Florida, Inc. ("1000 Friends"), Florida Bay Initiative,
Inc., the Florida Keys Fishing Guides Association, Michael Collins, Charles
W. Causey (collectively "FBII"), the Florida Keys Citizens Coalition, Inc.
("FKCC"), and A.G. Intus, Inc. ("Intus"), timely filed petitions pursuant
to Section 120.57, Fla. Stat. (1995), objecting to the District's intent
to issue the Management and Storage of Surface Waters and Wetland Resource
permits for the proposed project, and requesting formal administrative
hearings. FBII additionally objected to the District's intent to
modify a Right of Way/Occupancy permit for the proposed project.
The District
referred the cases to the Division of Administrative Hearings ("DOAH")
where they were assigned case numbers. On December 4, 1995, the petitions
were consolidated. On December 29, 1995, Monroe County filed a Petition
for leave to Intervene. That petition was granted in January of 1996.
Intus voluntarily
dismissed its case, and the hearing regarding the issues raised by the
other petitioners went to trial. A lengthy trial followed.
The parties submitted Proposed Recommended Orders, and on April 11, 1997,
the ALJ issued a Recommended Order "RO". It is the contention of
Petitioners/Appellants that the RO, and Final Order which adopted it, departed
from numerous requirements of law.
The most
central feature of this case was the consideration of the secondary and
cumulative impacts requirements. The Administrative Law Judge's Recommended
Order and the South Florida Water Management District's Final Order, with
respect to this matter both found a direct causal connection existed between
the widening of U.S.1. and additional development. They then proceeded
to find that Monroe County's Comprehensive Plan and land development regulations
and the Department of Community Affair's scrutiny of those regulations
"are intervening factors that break any causal relation . . ." (RO-FOF
at 54, 149; RO-COL at 95, 291) They specifically found
that hundreds of new building permits to be issued throughout the Florida
Keys were secondary impacts caused by the project. The ALJ then determined,
as a matter of law, that FDOT was relieved from the obligation to consider
the impacts of these additional residential units.
The ALJ
and SFWMD also improperly placed on the Petitioners the burden of proving
that environmental impacts would occur from the secondary impacts of the
development caused by the road widening project, stating as follows:
148. Although Petitioners
established there is a causal relation between the project and the existing
status of the law governing the number of building permits that can [sic]
issued in the future, the evidence was insufficient to establish at a level
above speculation that adverse environmental impacts will result because
of the issuance of those building permits. (RO-FOF at 54, 148)
This burden
should have been placed on FDOT, the applicant. The shifting of the
burden to the Petitioners was error. The ultimate burden of proof
to show that it has met all the requirements of law, of entitlement to
a permit, is always on the applicant. See, FDOT JWC Company, Inc.,
396 So.2d 778 (Fla. 1st DCA 1981).
Further,
still the ALJ and the District erred in concluding as a matter of law that
the FDOT did not have to assess the secondary impacts associated with the
second south bound lane. The project at issue contemplates a four
lane road bed with three lanes of pavement. The second south bound
lane would not yet be paved. The ALJ wrote in his Recommended Order
as follows:
267. Modifying the project
at a later date to pave the second southbound lane would require a District
ERP permit. The addition of impervious surface triggers the District's
SWM jurisdiction in this regard.
268. However, FDOT established
that it had no current plans for further widening. The permit conditions
require secondary and cumulative impacts associated with the increased
capacity be addressed in accordance with the rules and criteria in effect
at the time of any future widening. In addition, the permits require
that FDOT must comply with any more stringent water quality criteria in
affect at the time of any future widening.
It is FDOT's
responsibility to provide reasonable assurances prior to the issuance of
the permits that the entire build-out of the project will meet all applicable
standards and criteria. The agency cannot wait to study secondary
impacts later, when the second south bound lane is installed. Fla.
Keys Citizens Coalition and City of Key West v. 1800 Atlantic Developers
and Department of Environmental Regulation, 8 FALR 5564 (Final Order dated
October 17, 1986). Rudloe and Gulf Specimen Co., Inc. v. Dickerson
Bayshore, Inc. and Department of Environmental Regulation, 10 FALR 3426
(Final Order issued June 9, 1988), Concerned Citizens, supra at 5.
The FDOT has failed in its burden, and it is the position of Petitioners/Appellants
that the permits should not have been issued. These issues are on
appeal to both FLWAC and the Third District Court of Appeals. The
appeal to the District Court is stayed pending resolution of the review
by FLWAC.
Conclusion
The secondary
impacts analysis in wetland and surface water permitting, is and has been,
an evolving area of environmental law. The requirement is a potent
tool for environmental protection. It will be interesting to see
how the analysis is treated in future cases under the ERP.
Dionč Carroll is an attorney
for Lehtinen, O'Donnell, Vargas & Reiner, P.A., Miami, Florida.
She has been practicing with this firm from September, 1995 to present.
Her primary areas of practice are Environmental, Native American Tribal
and Civil Rights Law.
|